Support activities
Adding Support Activities
To use support activities, you must first add them.
Support activities can be added from the menu Settings → Support activities list. In the list that opens, click the “New” button in the header.
A blank support activity window will open. Fill in the following:
- Enter the code.
- Enter the name.
- Select the reporting logic:
Auto – always a standalone activity, not linked to any project/operation.
- Connected with operation – activities that are linked to the project/operation selected in the operator view. In other words, a support activity that is not added as an operation but becomes necessary during the execution of an operation.
Tick “Comment required” if you want adding a comment to be mandatory when completing the support activity. In the reporting module, a completion window with a text field will always be shown, where the user can enter a comment about the performed support activity.
Finally, click Save.
Enter all support activities in this way that you wish to track.
If you no longer want to use a support activity, tick the “Closed” checkbox.
Last updated: October 22, 2026